Please Post Your Answer to Worked Example 2.8

Please Post Your Answer to Worked Example 2.8 here.

Congratulation to Group B for the best correct answer.

Results for this worked example:
No. 1 is Group B
No. 2 is Group E
No. 3 is Group D
No. 4 is Group A
No. 5 is Group C

Total Score so far:
Group A= 2+5+1+1+4+4
Group B=4+2+2+2+2+1
Group C=5+1+5+3+3+5
Group D=3+4+3+4+5+3
Group E=1+3+4+5+1+2

Filed under 1 by

Spread the Word!

Permalink Print Comment

Comments on Please Post Your Answer to Worked Example 2.8 »

November 28, 2007

green_apple18 @ 12:30 pm

answer: 28.70m3/s

green_apple18 @ 12:31 pm

Group E
answer: 28.70m3/s

alexyap @ 12:34 pm

group B

answer = 21.94 m3/s

initial loss for 5min isochrones is taken as 8.28 mm and the 10min isochrones is taken as 1.72mm.

green_apple18 @ 12:34 pm

Group E
Answer: Qp = 28.70m3/s
Design P =86.21mm
tc: 25minutes
intial loss: 10mm

mdrajuna @ 1:20 pm

group c
Qp=30.68m3/s

Daphne @ 1:33 pm

Group A
28.7m3/sec

suhayati Abd Rahman @ 1:48 pm

Group E
Qp = 22.87m3/s
I = 206.9mm/hr
Fd = 0.19
tc = 25min
losses = initial 10mm,subsequently 20% of rainfall depth.

mdrajuna @ 2:01 pm

group c
QP=28.87m3/s

ipshl @ 2:05 pm

Group D:

Qp = 22.87 m3/s

Daphne @ 2:17 pm

Group A
Fd=0.19
Design I=206.9mm/hr Design P = 86.2055mm
Qp=28.7m3/s

alexyap @ 2:19 pm

group B revised

answer = 22.87 m3/s

initial loss for 5min isochrones is taken as 8.28 mm and the 10min isochrones is taken as 1.72mm.

p=86.23