Today is Day 2 of Workshop No. 1 at UTM, KL

Hello to All Participants,

Today is Day 2 of Workshop No. 1 at UTM, KL.

Below is the result of the competition for Day 1 (in order of completion time):

Worked Example 2.1- Team 1, 2, 4, 3
Worked Example 2.2- Team 1, 2, 3, 4
Worked Example 2.3- Team 1, 2, 4, 3
Worked Example 2.5- Team 4, 3, 2, 1
Worked Example 2.6- Team 4, 3, 2, 1
Worked Example 2.7- Team 1, 4, 3, 2
Worked Example 2.8- Team 1, 4, 2, 3
Worked Example 2.9- Team 4, 1, 2, 3
Worked Example 2.11- Draw
Worked Example 2.12- Draw

The results of the Worked Examples are:

Worked Example 2.2-Intensity i100=186.3 mm/hr, duration=30 min

Worked Example 2.3- Depth I50=129.75 mm at 60 min time interval

Worked Example 2.5- FD=0.598, tc=16 min, C=0.91, Q100=12.4 m3/s

Worked Example 2.6- FD=1.174, tc=8.4 min, C=0.9, Q100=34.1 m3/s

Worked Example 2.7
Q1- Upstream areas are outside catchment boundaries.
Q2-First rainfall burst reached and passed catchment outlet.

Worked Example 2.8- tc=25 min, Fd=0.19, I=206.9 mm/hr, Qp=22.9 m3/s

Worked Example 2.9- tc=35 min, I=112.8 mm/hr, Qp=16.08 m3/s

Worked Example 2.11- Q=8.706 m3/s, H=22.65 m RL

Worked Example 2.12- Q=8.4 m3/s, H=22.5 m RL

Regards,

Dr. Quek Keng Hong
21-3-2007

Filed under Uncategorized by

Spread the Word!

Permalink Print Comment

Comments on Today is Day 2 of Workshop No. 1 at UTM, KL »

March 21, 2007

ksyeap @ 8:53 am

This Is yeap/…

ksyeap @ 8:56 am

Hi this is yeap

Mr.Tie @ 11:39 am

hi.
this is tie king bang from Group 2

chanhoong @ 2:24 pm

Group 2 Answers to Workshop Example 2.9
16.08m3/s

Leave a Comment